FY09 Site Prep, Release, and PCT Project
Mechanical and prescribed burning site preparation, manual release, and pre-commercial thinning operations across the Caddo-Womble District.
Project Summary
Location Summary:
Various locations across the Caddo-Womle District
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/12/2008 |
Comment Period | 08/13/2008 |
Decision | 09/2008 (Estimated) |
Implementation | 10/2008 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Womble Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Vegetation Management (Other Than Forest Products)
Project Activity:
Forest Vegetation Improvements
Current Status:
Completed
Project Decision Information
FY09 Site Preparation, Planting, Release, and Pre-Commercial Thinning (PCT)
Decision Signed Date: 09/29/2008
Legal Notice Date: 10/01/2008
Forests:
Ouachita National Forest
Districts:
Womble Ranger District
States:
Arkansas
Counties:
Montgomery; Pike; Polk
Legal Land Description:
Various locations across the Caddo-Womle District
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
John Morgan
P.O. Box 255
Mount, AR 71957
870-867-2101
jcmorgan@fs.fed.us
Last Updated: 10/1/2008