Forest Road 19 Re-Route
Re-Route of an impassable portion of a Forest Service Road to include upgrading management levels of existing roads and constructing new road.
Project Summary
Location Summary:
Forest Road 19 and re-route segments to the east of that including road numbers 876, 19B, and S27 as well as new construction.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/03/2023 |
Decision | 07/2023 (Estimated) |
Implementation | 08/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Poteau Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Forest Road 19 Re-Route Decision
Decision Signed Date: 07/19/2023
Forests:
Ouachita National Forest
Districts:
Poteau Ranger District
States:
Arkansas
Counties:
Scott
Legal Land Description:
Township 4 North, Range 27 West, Sections 15, 22, 23, 26, 27, 28.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mary Newton
P.O. Box 2255
Waldron, AR 71958
000-000-0000
Mary.Newton@usda.gov
Last Updated: 7/19/2023