Oark Riparian Improvement Project
Improve riparian conditions and reduce erosion on the Mulberry River in the vicinity of Oark. (New name - previously known as "Mulberry River Stream and Riparian Restoration Project")
Project Summary
Current Status:
Completed
Location Summary:
T12N, R24W, Sections 19 & 20
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/26/2024 |
| Decision | 05/2024 (Estimated) |
| Implementation | 03/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (19), 36 Cfr 220.6(E)(19)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pleasant Hill Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Project Decision Information
Oark Riparian Improvement Project
Decision Signed Date: 05/31/2024
Forests:
Ozark-St. Francis National Forests
Districts:
Pleasant Hill Ranger District
States:
Arkansas
Counties:
Johnson
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Matthew Anderson
2591 Highway 21
Clarksville, AR 72830
479-964-7231
matthew.anderson4@usda.gov
Last Updated: 8/16/2024