Mulberry River Cane Restoration
River cane restoration along the Mulberry River on the Pleasant Hill Ranger District
Project Summary
Location Summary:
Recreation Sites along the Mulberry River, off of Highway 215.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/06/2022 |
Decision | 01/2023 (Estimated) |
Implementation | 01/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pleasant Hill Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments
Current Status:
Completed
Project Decision Information
Mulberry River Cane Restoration
Decision Signed Date: 01/18/2023
Forests:
Ozark-St. Francis National Forests
Districts:
Pleasant Hill Ranger District
States:
Arkansas
Counties:
Johnson
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Charles Stokes
2591 Highway 21
Clarksville, AR 72830
479-754-2864
Charles.Stokes@usda.gov
Last Updated: 1/19/2023