Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/11/2011 |
| Decision | 08/2011 (Estimated) |
| Implementation | 09/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Rochester Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Developed Site Management; Trail Management
Current Status:
Completed
Project Decision Information
Blueberry Lake Site Additions and Restoration Project
Decision Signed Date: 08/10/2011
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Rochester Ranger District
States:
Vermont
Counties:
Washington
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Holly Knox
99 Ranger Road
Rochester, VT 05767
802-747-6718
hknox@fs.fed.us
Last Updated: 9/29/2011