Mount Snow Fiber Optic Line Installation
This project is within the Mount Snow Ski Area managed under a special use permit. The project includes an 80 ft long trench, two ft deep, that will be dug between the top of Lift #17 to the Summit Lodge to carry fiber optic lines. Some blasting may be necessary. An existing 800 ft trench will be opened to replace a conduit with fiber optics.
Project Summary
Location Summary:
Manchester Ranger District, Town of Dover
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/01/2011 |
| Decision | 07/2011 (Estimated) |
| Implementation | 07/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Manchester Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Mount Snow Fiber Optic Line Installation Project
Decision Signed Date: 07/06/2011
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Manchester Ranger District
States:
Vermont
Counties:
Windham
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Thomas Paquette
2538 Depot Street
Manchester Center, VT 05255
802-767-4261 x 521
tpaquette@fs.fed.us
Last Updated: 8/12/2011