Warren Falls Parking Lot Expansion
Increase the size of the existing parking lot to safely provide access to the Warren Falls area along VT Route 100. Initially published as the "Warren Falls Site Improvements" project. The 30-day comment period ended on July 5, 2012. No comments of concern were received.
Project Summary
Location Summary:
Town of Warren
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/05/2012 |
Comment Period | 06/05/2012 |
Decision | 09/2012 (Estimated) |
Implementation | 08/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Rochester Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Developed Site Management; Trail Management
Current Status:
Completed
Project Decision Information
Warren Falls Parking Lot Expansion Project
Decision Signed Date: 09/18/2012
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Rochester Ranger District
States:
Vermont
Counties:
Washington
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Holly Knox
99 Ranger Road
Rochester, VT 05767
802-767-4261 x530
hknox@fs.fed.us
Last Updated: 9/27/2012