Bucklin Trail Relocation
Relocate a segment of Bucklin Trail that was damaged from Tropical Storm Irene to move it away from Brewers Brook. This is a popular Appalachian Trail/Long Trail sidetrail to acess Killington Peak. The 30-day comment period ended on July 5, 2012. No comments of concern were received.
Project Summary
Location Summary:
Town of Killington
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/05/2012 |
| Comment Period | 06/05/2012 |
| Decision | 07/2012 (Estimated) |
| Implementation | 08/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Manchester Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Recreation Management
Project Activity:
Trail Management
Current Status:
Completed
Project Decision Information
Bucklin Trail Re-route Project
Decision Signed Date: 07/11/2012
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Manchester Ranger District
States:
Vermont
Counties:
Rutland
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Carol Burd
2538 Depot Street
Manchester Center, VT 05255
802-747-6749
cburd@fs.fed.us
Last Updated: 9/28/2012