Abbey Pond Trail Relocations
Relocate approximately 0.5 mile of the Abbey Pond Trail to remove portions of the trail from wetland locations and improve open water crossings. The purpose of the project is to protect wetland resources and improve safety. The 30-day comment period ended on May 2, 2013. No comments of concern were received thus there is no appeal opportunity.
Project Summary
Location Summary:
Towns of Middlebury and Ripton
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/02/2013 |
| Comment Period | 04/02/2013 |
| Decision | 05/2013 (Estimated) |
| Implementation | 07/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Middlebury Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Watershed Management; Recreation Management
Project Activity:
Trail Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
Abbey Pond Trail Relocation Project
Decision Signed Date: 05/24/2013
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Middlebury Ranger District
States:
Vermont
Counties:
Addison
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Holly Knox
1007 Route 7 South
Middlebury, VT 05753
802-767-4261 x530
hknox@fs.fed.us
Last Updated: 5/29/2013