Sugarbush In Road Trail Relocation
Construct new 75 foot approach to In Road Trail which connects Easy Rider Trail to Out to Lunch Trail to improve site distance and grade. Approximately 10 trees would be removed, stumps pulled and trail graded for a total of about 1,200 square feet.
Project Summary
Location Summary:
Town of Warren
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/01/2013 |
| Comment Period | 07/01/2013 |
| Decision | 09/2013 (Estimated) |
| Implementation | 09/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Rochester Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management; Recreation Management
Project Activity:
Developed Site Management; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Sugarbush Inroad Tral Improvement
Decision Signed Date: 09/06/2013
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Rochester Ranger District
States:
Vermont
Counties:
Washington
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Thomas Paquette
99 Ranger Road
Rochester, VT 05767
802-767-4261 x 521
tpaquette@fs.fed.us
Last Updated: 9/29/2013