Sawmill Creek Wetland Restoration
Enhance wetland function and reduce erosion around a recovering wetland by re-establishing original wetland outlet and dimensions, dismantling old drainage ditches, and reducing flow through a failing culvert draining into a deeply eroding gully.
Project Summary
Location Summary:
Town of Hector
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/09/2018 |
| Decision | 04/2018 (Estimated) |
| Implementation | 08/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Hector Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management
Project Activity:
Species Habitat Improvements; Noxious Weed Treatments; Special Area Management; Watershed Improvements
Current Status:
Completed
Project Decision Information
Sawmill Creek Wetland Restoration
Decision Signed Date: 04/20/2018
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Hector Ranger District
States:
New York
Counties:
Schuyler
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Angelica Quintana
5218 State Route 414
Hector, NY 14841
802-747-6742
angelicaquintana@fs.fed.us
Last Updated: 4/24/2018