Lincoln Peak Communications Site Expansion Special Use
VELCO proposes to improve worker safety and emergency response by replacing their 10 foot tower with a taller tower and consolidating all other site users under the authority of an amendment to the Lincoln Peak Electronics Site Association Permit.
Project Summary
Location Summary:
Town of Warren
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/07/2019 |
Decision | 03/2019 (Estimated) |
Implementation | 09/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Rochester Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Lincoln Peak Communications Site Expansion Special Use
Decision Signed Date: 03/07/2019
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Rochester Ranger District
States:
Vermont
Counties:
Washington
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jennifer Edmonds
99 Ranger Road
Rochester, VT 05767
802-747-6746
jedmonds@fs.fed.us
Last Updated: 3/12/2019