Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/15/2022 |
| Decision | 09/2022 (Estimated) |
| Implementation | 10/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Rochester Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management; Recreation Management
Project Activity:
Developed Site Management; Trail Management
Current Status:
Completed
Project Decision Information
Sugarbush Reverse Traverse Realignment and Snowmaking
Decision Signed Date: 09/02/2022
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Rochester Ranger District
States:
Vermont
Counties:
Washington
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeffrey Hammell
99 Ranger Road
Rochester, VT 05767
802-222-1828
jeffrey.hammell@usda.gov
Last Updated: 11/28/2022