Mount Snow High Traverse Widening
Widen the High Traverse alpine ski trail to relieve congestion, replace 400 feet of buried power line along the trail and add a valve house in the same vicinity to improve snowmaking efficiency.
Project Summary
Location Summary:
Town of Dover
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/15/2023 |
Decision | 03/2024 (Estimated) |
Implementation | 04/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Manchester Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Facility Improvements/Construction
Current Status:
Completed
Project Decision Information
Mount Snow High Traverse Widening
Decision Signed Date: 03/19/2024
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Manchester Ranger District
States:
Vermont
Counties:
Windham
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nathaniel Blanks
2538 Depot Street
Manchester Center, VT 05255
802-747-6714
Nathaniel.Blanks@usda.gov
Last Updated: 4/25/2024