Hogback Loop Trail Realignment
Realignment of the Hogback Loop Trail (Catamount Trail) near the privately owned Blueberry Hill Inn. Construction of 0.14 miles of Class 4 Cross Country Ski Trail and a bridge, culvert, or ford. Decommissioning of 0.7 miles of ski trail.
Project Summary
Location Summary:
Town of Goshen
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/06/2023 |
Decision | 09/2023 (Estimated) |
Implementation | 11/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Middlebury Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management
Project Activity:
Dispersed Recreation Mgmt.
Current Status:
Completed
Project Decision Information
Hogback Loop Trail Realignment
Decision Signed Date: 09/25/2023
Forests:
Green Mountain And Finger Lakes National Forests
Districts:
Middlebury Ranger District
States:
Vermont
Counties:
Addison
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Philip MacAskill
1007 Route 7 South
Middlebury, VT 05753
802-767-4261 x5530
philip.macaskill@usda.gov
Last Updated: 9/26/2023