Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/03/2016 |
Decision | 05/2016 (Estimated) |
Implementation | 06/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Wayne National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Natural Gas; Oil
Current Status:
Completed
Project Decision Information
Precision Geophysical Inc. Seismic Testing
Decision Signed Date: 05/23/2016
Forests:
Wayne National Forest
Districts:
Wayne National Forest All Units
States:
Ohio
Counties:
Lawrence; Noble; Washington
Legal Land Description:
Sec.18 T4N, R7W Elk Township; Sec. 8,9,13-17,22,23,31&33 T4N, R7W Liberty Township; Sec. 24,30&34 T3N, R7W Lawrence Township
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Steve Sapio
13700 US Highway 33
Nelsonville, OH 45764
740-373-5046
ssapio@fs.fed.us
Last Updated: 5/26/2016