|
|
Changing the Requirements
Some situations may require changes to existing contract requirements
or
crew instructions. If you determine that a contract's requirements
will not provide for adequate tree survival and growth, coordinate
with your silviculturist or other specialists and the CO and proceed
to change the requirements. It is better to negotiate contract adjustments
or modifications than to plant trees under a contract with unsuitable
clauses that result in a plantation failure. It is generally wise
to negotiate with the contractor and make appropriate cost adjustments.
In some cases, the changes will be unilateral. Involve the CO in
these
negotiations and contract changes.
The following examples show some good and bad decisions for modifying
a contract's requirements. These are merely examples. Many exceptions
exist.
Smart Decisions
- Since the time of the contract's award, grass has invaded
the planting unit. Scalping is needed, although it was not required
originally.
Adding scalping to the unit requirements is a good decision. Expect
an increased cost.
- Fewer trees are available than expected for
a planting unit because of a nursery underrun. Rather than plant
only a portion of the
unit, the objectives could be met by planting at a slightly wider spacing.
Widening the spacing would be a good decision, and usually would
reduce the unit price.
- The contractor is delayed 1 week and he requests
an extension of the contract. If there is good soil moisture, if
trees are still
dormant and in good shape, and if weather and other conditions
will hold, it is probably okay to extend the length of the contract, because
doing so won’t affect survival. A contract cost reduction
may be appropriate to compensate for the delay. (top)
Poor Decisions
- The contractor’s time is running out. Even though the weather
is hot and windy, the contractor has the whole crew at the district,
trees are ready to be planted, and the contractor wants to plant
through the day. The contract states that the contractor is not
to plant during unfavorable weather conditions. It would probably
be
a bad decision to allow the contractor to plant, unless the effects
of the hot and windy weather on the seedlings' survival can be
mitigated. Determine whether conditions are more favorable at another
unit,
and whether the crew could be moved instead of shut down. Also,
consider the effects of windy conditions on contractor safety.
If the area
has snags, allowing the contractor to plant may be a poor decision.
- The
contract requires a 24-inch scalp because of heavy grass competition.
The 24-inch scalp was determined to be the minimum necessary
to achieve survival. The contractor is having problems getting
a 24-inch scalp
with the hoedad, so he asks to have the scalp reduced to 12 inches.
It would probably be a poor decision to change the scalp size,
because 24 inches is the minimum needed for survival. The contractor should
have considered the difficulty of scalping when making the bid
and selected an appropriate tool to meet the requirements. If the contract
misrepresented the difficulty of scalping, a cost adjustment
may be in order. Do not reduce scalp size just because it is difficult
to make a scalp that meets the requirements.
|