Alpine Tunnel ARRA project
The project involves installing new interpretive signs, stabilizing historic stone structures, stabilizing the stone west portal and entrance to the Alpine Tunnel, and some rerouting sections of trail.
Project Summary
Location Summary:
Alpine Tunnel, Gunnison Ranger District, GMUG NF
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/10/2009 |
Decision | 09/2009 (Estimated) |
Implementation | 07/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (5), 36 Cfr 220.6(D)(5)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Gunnison Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Heritage Resource Management; Recreation Management
Project Activity:
Developed Site Management; Heritage Resource Management; Trail Management
Current Status:
Completed
Project Decision Information
Alpine Tunnel - ARRA
Decision Signed Date: 09/21/2009
Forests:
Grand Mesa, Uncompahgre and Gunnison National Forests
Districts:
Gunnison Ranger District
States:
Colorado
Counties:
Gunnison
Legal Land Description:
Alpine Tunnel
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Ray Rossman
216 N. Colorado
Gunnison, CO 81230
970-642-4435
rrossman@fs.fed.us
Last Updated: 4/3/2013