Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/04/2016 |
Decision | 11/2018 (Estimated) |
Implementation | 07/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Gunnison Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Cunningham Ditch Reconstruction
Decision Signed Date: 11/06/2018
Forests:
Grand Mesa, Uncompahgre and Gunnison National Forests
Districts:
Gunnison Ranger District
States:
Colorado
Counties:
Gunnison
Legal Land Description:
NW 1/4, Sec 11, T51N, R2W, NMPM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Bennie South
216 N. Colorado
Gunnison, CO 81230
970-641-0471
bsouth@fs.fed.us
Last Updated: 9/27/2019