Windy Ridge Communication Site Road Realignment
Proposal to re-align existing administrative use road FSR 961 to ensure safe and reliable access to Windy Ridge Communication Site infrastructure.
Project Summary
Location Summary:
Windy Ridge Communication Site, Windy Mountain
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/24/2022 |
Comment Period | 11/26/2024 |
Decision | 05/2025 (Estimated) |
Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Wind River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Decommissioning; Road Maintenance; Road Improvements/Construction
Current Status:
In Progress
Forests:
Shoshone National Forest
Districts:
Wind River Ranger District
States:
Wyoming
Counties:
Fremont
Legal Land Description:
Section 21, 22, T. 41 N., R. 107 W. 6th Principal Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Seth Halman
1403 W Ramshorn
Dubois, WY 82513-0186
307-455-4157
seth.halman@usda.gov
Last Updated: 1/13/2025