Energen Resources Corporation Oil and Gas Production Facility Special Use Authorization
The Forest Service is proposing to issue a special use permit to Energen Resources Corporation (Energen)for the purpose of occupying National Forest System lands to drill four off lease natural gas wells by expanding an existing Energen well pad.
Project Summary
Location Summary:
Section 10, Township 32 North, Range 5 West, Carracas Mesa
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 07/08/2014 |
Comment Period | 01/01/2015 |
Objection Period Start | 03/19/2015 |
Decision | 05/2015 (Estimated) |
Implementation | 05/2015 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Jicarilla Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Special Use Management; Minerals And Geology
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Energen Resources Corp Oil and Gas Production Facility Special Use Auth
Decision Signed Date: 05/18/2015
Forests:
Carson National Forest
Districts:
Jicarilla Ranger District
States:
New Mexico
Counties:
Rio Arriba
Legal Land Description:
Section 10, Township 32 North, Range 5 West, NMPM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Patrick Yamnik
1110 Rio Vista Lane, Unit #2
Bloomfield, NM 87413
505-632-2956
comments-southwestern-carson-jicarilla@fs.fed.us
Last Updated: 6/11/2021