Martinez Acequia Secondary Inlet Structure
Proposed installation of a water control structure (headgate) to control erosion, divert water into the Martinez acequia, and return excess water to its historic channel. Installation includes steel wingwalls and weir, gabion baskets, and rip-rap.
Project Summary
Location Summary:
Project area is on the south side of NM Highway 518, west of Forest Road 89.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 12/09/2015 |
Decision | 09/2016 (Estimated) |
Implementation | 09/2016 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Camino Real Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Martinez Acequia Secondary Inlet Structure
Decision Signed Date: 09/12/2016
Forests:
Carson National Forest
Districts:
Camino Real Ranger District
States:
New Mexico
Counties:
Taos
Legal Land Description:
Township 22 North, Range 14 East, Section 30, New Mexico Principal Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Paul Schilke
P.O. Box 68
Penasco, NM 87553
575-587-2255
comments-southwestern-carson-caminoreal@fs.fed.us
Last Updated: 9/13/2016