Plan of Operations, Minerals Exploration, Hermosa Drilling Project
Exploration and geotechnical drilling, monitoring well installation, and test trenching at 46 locations. Includes temporary access roads, overland travel, foot travel, road maintenance on existing roads, and well monitoring.
Project Summary
Location Summary:
Approximately 6 miles SE of Patagonia, AZ
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/06/2013 |
Comment Period | 03/07/2014 |
Objection Period Start | 09/2015 (Estimated) |
Decision | 01/2016 (Estimated) |
Implementation | 02/2016 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sierra Vista Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Cancelled
Forests:
Coronado National Forest
Districts:
Sierra Vista Ranger District
States:
Arizona
Counties:
Santa Cruz
Legal Land Description:
Sections 33, 34, 35, 36, T 22 S, R 16 E, Sections 1, 2, 3, 4, 5, 9, 10, 11, 12, 14, 15, 16, T 23 S, R 16 E, and Sections 6, 7, T 22 S, R 17 E.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Richard Goshen
5990 S. Hwy. 92
Hereford, AZ 85615
520-388-8341
rgoshen@fs.fed.us