Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/18/2007 |
Comment Period | 02/04/2010 |
Decision | 11/2010 (Estimated) |
Implementation | 03/2011 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sierra Vista Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements
Current Status:
Completed
Project Decision Information
Redrock Canyon Habitat Renovation
Decision Signed Date: 11/05/2010
Legal Notice Date: 11/12/2010
Forests:
Coronado National Forest
Districts:
Sierra Vista Ranger District
States:
Arizona
Counties:
Santa Cruz
Legal Land Description:
T22S, R17E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Glenn Frederick
5990 S. Hwy. 92
Hereford, AZ 85615
520-803-2827
gfrederick@fs.fed.us
Last Updated: 11/15/2010