Reroute of Forest System Road 159, High Creek Road
Maintain, construct and reconstruct a road that will connect Harrison Canyon Road and High Creek Road.
Project Summary
Location Summary:
Eastern side of the Gailuro Mountains
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/24/2009 |
| Comment Period | 08/28/2009 |
| Decision | 11/2009 (Estimated) |
| Implementation | 01/2010 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Safford Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Road Management
Project Activity:
Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Restoration of Vehicle Access to High Creek Road, NFSR 159
Decision Signed Date: 11/05/2009
(FS Withdrawn)
Legal Notice Date: 11/15/2009
Restoration of Vehicle Access to High Creek Road, NFSR 159
Decision Signed Date: 11/05/2009
Legal Notice Date: 11/15/2009
Forests:
Coronado National Forest
Districts:
Safford Ranger District
States:
Arizona
Counties:
Graham
Legal Land Description:
Section 17, Township 10 South, Range 21 East, Gila and Salt River Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Debra Mollet
P.O. Box 709
Safford, AZ 85548-0709
520-388-8415
dmollet@fs.fed.us
Last Updated: 12/9/2009