Tanbark Adit Bat Gate
Reclosure of an Abandoned Mineland feature that had been reopened due to vandalism. Adit will be closed with bat-friendly gating to prevent human entry in order to protect bat habitat from human disturbance and to provide for public safety.
Project Summary
Current Status:
Completed
Location Summary:
The adit is in the vicinity of FR 108
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/25/2020 |
| Decision | 02/2022 (Estimated) |
| Implementation | 08/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Smokey Bear Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Abandoned Mine Land Clean-Up
Project Decision Information
Tanbark Adit Bat Gate Project Decision Memo
Decision Signed Date: 02/01/2022
Forests:
Lincoln National Forest
Districts:
Smokey Bear Ranger District
States:
New Mexico
Counties:
Lincoln
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christina Thompson
901 Mechem Drive
Ruidoso, NM 88345
575-257-4095
cmthompson@fs.fed.us
Last Updated: 2/2/2022