Otero County Electric Cooperative Range Powerline
Construct approximately 300 feet of primary overhead line, and 2 new poles with guy wires to supply power to operate a well that supplies water for livestock and wildlife on a grazing allotment.
Project Summary
Location Summary:
Scott Able Allotment
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/01/2018 |
| Decision | 03/2018 (Estimated) |
| Implementation | 03/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sacramento Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Otero County Electric Cooperative Range Powerline
Decision Signed Date: 03/02/2018
Forests:
Lincoln National Forest
Districts:
Sacramento Ranger District
States:
New Mexico
Counties:
Otero
Legal Land Description:
T. 18 S., R. 12 E.; Section 21
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Marcie Kelton
P.O. Box 288
Cloudcroft, NM 88317
575-682-2551
marciekelton@fs.fed.us
Last Updated: 3/5/2018