Red Lake/ Turkey Canyon Water Improvement Project
The Lincoln National Forest, Guadalupe Ranger District is proposing to authorize the installation of 6 water troughs and their storage tanks to provide permanent, yearlong waters to wildlife and livestock in the Red Lake/ Turkey Canyon area.
Project Summary
Location Summary:
The project area is located north and south of state highway 137 east of Queen, New Mexico
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/13/2018 |
Decision | 10/2018 (Estimated) |
Implementation | 11/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (6), 36 Cfr 220.6(E)(6)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Guadalupe Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements
Current Status:
Completed
Project Decision Information
Red Lake/ Turkey Canyon Water Improvement Project
Decision Signed Date: 10/23/2018
Forests:
Lincoln National Forest
Districts:
Guadalupe Ranger District
States:
New Mexico
Counties:
Eddy
Legal Land Description:
The legal location is on multiple Sections of Township 24 South /Range 22 East and multiple sections of Township 25 South /Range 22 East.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Renae Cox
Federal Bldg., Rm 159
Carlsbad, NM 88220
575-885-4181
rcox@fs.fed.us
Last Updated: 10/24/2018