Radio Facility Construction Sacramento Peak
Forest Service is proposing to conduct improvements (e.g. removal and replacement) on an existing radio facility located on Sacramento Peak. The action is needed to bring the site into compliance current guidance and ensure proper protection.
Project Summary
Location Summary:
The radio facility is located 15 miles southeast of Alamogordo, New Mexico.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/17/2019 |
Decision | 11/2019 (Estimated) |
Implementation | 11/2019 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Sacramento Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Facility Management
Project Activity:
Facility Improvements/Construction
Current Status:
Completed
Project Decision Information
Radio Facility Construction Sacramento Peak
Decision Signed Date: 11/01/2019
Forests:
Lincoln National Forest
Districts:
Sacramento Ranger District
States:
New Mexico
Counties:
Otero
Legal Land Description:
Township 18 South, Range 12 East, Section 18, New Mexico Meridian.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Andres Bolanos
P.O. Box 288
Cloudcroft, NM 88317
575-682-5315
andresbolanos@fs.fed.us
Last Updated: 11/5/2019