North Fork Eagle Creek Wells Control Building Expansion
Village of Ruidoso proposes to expand an existing building which houses water monitoring equipment in the North Fork Eagle Creek wellfield. The 7.3' x 7.3' building would double in size. Total surface disturbance would be less than 0.5 acres.
Project Summary
Location Summary:
North Fork Eagle Creek drainage along FS Road 127A approximately 4 miles northwest of Ruidoso, New Mexico.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 12/07/2022 |
| Decision | 01/2023 (Estimated) |
| Implementation | 01/2023 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Smokey Bear Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
North Fork Eagle Creek Wells Control Building Expansion
Decision Signed Date: 01/13/2023
Forests:
Lincoln National Forest
Districts:
Smokey Bear Ranger District
States:
New Mexico
Counties:
Lincoln
Legal Land Description:
Section 36 of T. 10 S., R. 12 E., NMPM
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Christina Thompson
901 Mechem Drive
Ruidoso, NM 88345
575-630-3050
christina.thompson@usda.gov
Last Updated: 1/13/2023