Crystal Creek--Gros Ventre Confluence Bio-Engineering Project
the Forest Service will relocate campground infrastructure to higher ground and install bioengineered bank stabilization treatments in along the Gros Ventre Road, and bioengineered streambank restoration work will also occur adjacent to Crystal Creek
Project Summary
Current Status:
Completed
Location Summary:
Confluence of Gros Ventre River and Crystal Creek, east of Kelly, Wyoming.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/04/2022 |
| Decision | 09/2022 (Estimated) |
| Implementation | 10/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (19), 36 Cfr 220.6(E)(19)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Jackson Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Climate Change Adaptation
Project Activity:
Watershed Improvements
Project Decision Information
Crystal Creek--Gros Ventre Confluence Bio-Engineering Project
Decision Signed Date: 09/15/2022
Forests:
Bridger-Teton National Forest
Districts:
Jackson Ranger District
States:
Wyoming
Counties:
Teton
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
David Cernicek
25 Rosencrans Lane
Jackson, WY 83001
307-739-5417
david.cernicek@usda.gov