Riley Ridge Natural Gas Development (Forest Service Portion)
Authorization of one existing gas well & construction of approximately 1,200 feet of buried pipeline. The final decision on the FS portion are available. One objection was received -- click on DECISION tab below to read more.
Project Summary
Location Summary:
Approximately 20 miles west of Big Piney, Wyoming
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/12/2014 |
Comment Period | 03/12/2014 |
Objection Period Start | 05/19/2017 |
Decision | 07/2019 (Estimated) |
Implementation | 06/2020 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Big Piney Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Riley Ridge Natural Gas Development (Forest Service Portion)
Decision Signed Date: 07/26/2019
Forests:
Bridger-Teton National Forest
Districts:
Big Piney Ranger District
States:
Wyoming
Counties:
Sublette
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Justin Snyder
10418 South US Highway 189
Big Piney, WY 83113
307 367 5740
justinsnyder@fs.fed.us
Last Updated: 7/30/2019