Jackson Hole Mountain Resort Proposed Mountain Improvements 2021--infrastructure
Five infrastructure additions: A new ski patrol station under the top Tram dock. A new garage for the Rendezvous Peak snowcat. A new kids play zone at Solitude Station. Viewing platforms on Rendezvous Peak. Relocation of an Avalanche Pipe Cannon.
Project Summary
Location Summary:
Jackson Hole Mountain Resort, Teton Village, WY
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 03/29/2021 |
Decision | 04/2021 (Estimated) |
Implementation | 06/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Jackson Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Facility Improvements/Construction; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Jackson Hole Mountain Resort Proposed Mountain Improvements 2021--infrastructure
Decision Signed Date: 04/30/2021
Forests:
Bridger-Teton National Forest
Districts:
Jackson Ranger District
States:
Wyoming
Counties:
Teton
Legal Land Description:
43 35%u2019 50%u201D N, 110 52%u2019 13%u201D W
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Sean McGinness
25 Rosencrans Lane
Jackson, WY 83001
209-295-4252
smcginness@fs.fed.us
Last Updated: 5/3/2021