Lava Creek Fish Passage
Partnership between the Forest Service and Trout Unlimited to improve fish habitat and connectivity by redesigning diversion dams on Lava Creek.
Project Summary
Location Summary:
North of US Hwy 26, about 2.5 miles east of Moran, WY.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/24/2024 |
Decision | 08/2024 (Estimated) |
Implementation | 10/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Buffalo Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Climate Change Adaptation; Watershed Management; Wildlife, Fish, Rare Plants
Project Activity:
Species Habitat Improvements
Current Status:
Completed
Project Decision Information
Lava Creek Fish Passage
Decision Signed Date: 08/22/2024
Forests:
Bridger-Teton National Forest
Districts:
Buffalo Ranger District
States:
Wyoming
Counties:
Teton
Legal Land Description:
T. 45 N., R. 113 W, Sec. 20 & 29, Sixth principal meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Chance Roberts
Hwy 26/287
Moran, WY 83013
505-720-2310
thomas.roberts@usda.gov
Last Updated: 9/6/2024