Muddy Creek Water Quality Improvement Project
Construct an in-stream diversion, off-stream sediment basin (off Forest), and pipeline along Muddy Creek (On FS lands) north of the town of Emery, Utah. Add the existing Emery Canal to the Special Uses Permit. The canal has been present since 1880s.
Project Summary
Current Status:
Completed
Location Summary:
Muddy Creek Canyon, just west of County Road 806
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/10/2009 |
| Decision | 10/2009 (Estimated) |
| Implementation | 03/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (4)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Ferron Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Project Decision Information
Muddy Creek Water Quality Improvement Project
Decision Signed Date: 10/21/2009
Forests:
Manti-Lasal National Forest
Districts:
Ferron Ranger District
States:
Utah
Counties:
Emery
Legal Land Description:
T21S, R6E, Sec. 21 approximately 4 miles north of Emery in Emery County, Utah
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Nathan Lewis
115 W. Canyon Rd
Ferron, UT 84523
435-636-3515
ndlewis@fs.fed.us
Last Updated: 4/6/2010