Middle Fork Blowdown
Salvage of blowdown timber in the Middle Fork of the Weiser River watershed. This occurred with a wind event in early June, 2010.
Project Summary
Current Status:
Completed
Location Summary:
Approximately 11 miles air miles east of Council, ID.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 07/29/2010 |
| Decision | 10/2010 (Estimated) |
| Implementation | 10/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (13), 36 Cfr 220.6(E)(13)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Council Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products
Project Activity:
Timber Sales (Salvage)
Project Decision Information
Middle Fork Blowdown
Decision Signed Date: 10/14/2010
Forests:
Payette National Forest
Districts:
Council Ranger District
States:
Idaho
Counties:
Adams
Legal Land Description:
Twp. 16N Rge. 2E, Boise Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Stephen Penny
P.O. Box 567
Council, ID 83612
208-253-0164
spenny@fs.fed.us