Pioneer Creek Water Intake and Screen Project
The proposed action would replace the existing Pioneer Creek water intake structure at the University of Idaho Taylor Ranch.
Project Summary
Location Summary:
Pioneer Creek a tributary of Big Creek in the FC-RONR Wilderness
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 04/26/2012 |
| Decision | 05/2012 (Estimated) |
| Implementation | 06/2012 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (8), 36 Cfr 220.6(D)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Krassel Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Cancelled
Forests:
Payette National Forest
Districts:
Krassel Ranger District
States:
Idaho
Counties:
Valley
Legal Land Description:
T. 20 N., R 13 E., Section 3; Boise Meridian, Valley County, Idaho
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jeff Hunteman
500 North Mission Street, Bldg 1
McCall, ID 83638
208-634-0434
jhunteman@fs.fed.us
Last Updated: 6/15/2012