St. Helens Mine Plan of Operations
Respond to a plan to mine 37,000 CY of volcanic rocks as supply chemical soil amendment over the course of 10 years from 5 acres of unpatented mining claims on NFS lands and determine need for any reasonable changes or additions to meet requirements of 36 CFR 228A, prior to approval.
Project Summary
Location Summary:
5.8 miles northwest of McCall, ID
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/03/2021 |
Comment Period | 02/04/2022 |
Objection Period Start | 06/02/2022 |
Decision | 08/2022 (Estimated) |
Implementation | 09/2022 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
McCall Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
St. Helens Mine Plan of Operations
Decision Signed Date: 08/03/2022
Forests:
Payette National Forest
Districts:
McCall Ranger District
States:
Idaho
Counties:
Adams
Legal Land Description:
T19N, R2E, sections 23, 24, 25 & 26, Boise Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Clinton Hughes
102 West Lake Street
McCall, ID 83638
208-983-5146