Warm Springs Trail #203 Reroute
Post Mesa Fire erosion of Warm Springs Creek has compromised a section of Trail #203. Rerouting the trail up the hillside would provide for safety of trail users, a sustainable trail tread, limit trail-caused erosion, and achieve USFS trail standards
Project Summary
Location Summary:
Reroute work would be performed on Trail #203, along Warm Springs Creek in the Middle Fork Weiser River drainage.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/22/2021 |
Decision | 08/2021 (Estimated) |
Implementation | 08/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (1), 36 Cfr 220.6(E)(1)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Council Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management; Recreation Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Warm Springs Trail #203 Reroute
Decision Signed Date: 08/10/2021
Forests:
Payette National Forest
Districts:
Council Ranger District
States:
Idaho
Counties:
Adams
Legal Land Description:
T15N, R1E, Sec 11
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jascha Zeitlin
P.O. Box 567
Council, ID 83612
208-549-4224
jzeitlin02@fs.fed.us
Last Updated: 8/10/2021