Big Creek Work Center Water Systems Upgrade Project
The PNF is proposing to upgrade water system infrastructure at the Big Creek Work Center including irrigation systems, water tanks, and stream flow measuring flumes. These upgrades will improve irrigation and provide potable water.
Project Summary
Location Summary:
Project is located at the Payette National Forest Big Creek Work Center and Airfield located along NFS Road 50340.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/01/2023 |
Decision | 05/2024 (Estimated) |
Implementation | 07/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (21), 36 Cfr 220.6(E)(21)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Krassel Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Facility Management
Project Activity:
Facility Improvements/Construction
Current Status:
Completed
Project Decision Information
Big Creek Work Center Water Systems Upgrade Project
Decision Signed Date: 05/29/2024
Forests:
Payette National Forest
Districts:
Krassel Ranger District
States:
Idaho
Counties:
Valley
Legal Land Description:
Township 21N, Range 12E, Section 24 Boise Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Samuel Thompson
500 North Mission Street, Bldg 1
McCall, ID 83638
208-634-0600
FS-comments-intermnt-payette@usda.gov
Last Updated: 9/17/2024