Burke Creek Restoration Project
Restoration of Burke Creek through Rabe Meadow to the mouth at Lake Tahoe. Existing Jennings Pond will be returned to a natural floodplain meadow. A new channel and mouth will be constructed adjacent to the campground. Fill Kahle ditch.
Project Summary
Current Status:
Completed
Location Summary:
Stateline, NV
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 02/21/2023 |
| Decision | 04/2024 (Estimated) |
| Implementation | 07/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (25), 36 Cfr 220.6(E)(25)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lake Tahoe Basin Mgt Unit
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Watershed Management
Project Activity:
Watershed Improvements
Project Decision Information
BURKE CREEK RABE MEADOW RIPARIAN RESTORATION PROJECT
Decision Signed Date: 04/02/2024
Forests:
Lake Tahoe Basin Mgt Unit
Districts:
Lake Tahoe Basin Mgt Unit
States:
Nevada
Counties:
Douglas
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Theresa Cody
35 College Drive
South Lake Tahoe, CA 96150
530-543-2788
theresa.cody@usda.gov
Last Updated: 12/13/2024