PG&E Mt Hough Comm Site Wood Product Removal
PG&E will treat 310 trees felled in 2024 as part of Mt Hough communications site electric line reinstallation.
Project Summary
Location Summary:
T26N, R10E, sections 8, 9, 10, 34. T25N, R10E, section 3
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 05/2025 (Estimated) |
Decision | 06/2025 (Estimated) |
Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Plumas National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Vegetation Management (Other Than Forest Products)
Project Activity:
Forest Vegetation Improvements
Current Status:
Developing Proposal
Forests:
Plumas National Forest
Districts:
Plumas National Forest All Units
States:
California
Counties:
Plumas
Legal Land Description:
T26N, R10E, sections 8, 9, 10, 34. T25N, R10E, section 3.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jacob Sax
159 Lawrence Street
Quincy, CA 95971-6025
530-927-8114
Jacob.Sax@usda.gov
Last Updated: 4/30/2025