Rapala Ridge Road Construction Project
A 500 foot road segment would be constructed on National Forest System land in order to provide access to Soper Company land.
Project Summary
Location Summary:
The road segment would be constructed at the end of NFS road 24N26A south of Thompson Valley.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 10/14/2009 |
| Decision | 01/2010 (Estimated) |
| Implementation | 05/2010 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mt. Hough Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Improvements/Construction
Current Status:
Completed
Project Decision Information
Rapala Ridge Road Construction Project
Decision Signed Date: 01/21/2010
Forests:
Plumas National Forest
Districts:
Mt. Hough Ranger District
States:
California
Counties:
Plumas
Legal Land Description:
T24N, R10E, Section 28
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Katherine Carpenter
39696 State Highway 70
Quincy, CA 95971
530-283-7619
kacarpenter@fs.fed.us
Last Updated: 3/4/2010