Challenge Substation Salvage
Salvage 5 large ponderosa pines cut at Pacific Gas and Electric Company substation for line protection.
Project Summary
Location Summary:
Immediately east of, and along side of, intersection of LaPorte and Old LaPorte roads
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 06/23/2015 |
| Decision | 07/2015 (Estimated) |
| Implementation | 07/2015 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (14), 36 Cfr 220.6(E)(14)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Feather River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Forest Products; Special Use Management
Project Activity:
Timber Sales (Salvage)
Current Status:
Completed
Project Decision Information
Challenge Substation Salvage
Decision Signed Date: 07/01/2015
Forests:
Plumas National Forest
Districts:
Feather River Ranger District
States:
California
Counties:
Yuba
Legal Land Description:
T19N R7E SW1/4 Section 20
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Eric Murphy
875 Mitchell Avenue
Oroville, CA 95965-4699
530-532-8922
ejmurphy@fs.fed.us
Last Updated: 12/10/2019