Aurora Rose Mining Project
Excavation of mineralized rock vein using hand tools such as shovels, picks, hand operated drills. Minor road repairs to .3 miles of 4WD access road including filling in holes and brushing with loppers. Long term camping at the claim while mining.
Project Summary
Location Summary:
The legal location of the project is T26N, R12E, Section 36, MDBM. The project area is southeast of Babcock Peak, off NFS Road 26N53.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 09/19/2018 |
Comment Period | 05/08/2019 |
Decision | 06/2019 (Estimated) |
Implementation | 06/2019 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Beckwourth Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Aurora Rose Mining Project
Decision Signed Date: 06/28/2019
Forests:
Plumas National Forest
Districts:
Beckwourth Ranger District
States:
California
Counties:
Plumas
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Leslie Edlund
23 Mohawk Road
Blairsden, CA 96103
530-283-7650
ledlund@fs.fed.us
Last Updated: 7/26/2019