Plumas Imperial Mining Plan of Operations
Plan of Operation submitted to mine using heavy equipment to excavate material, processing through a trommel and use of settling ponds. .5 miles of non-system road was constructed under a previous plan. This road will be maintained.
Project Summary
Location Summary:
Near Meadow Valley, CA
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/25/2019 |
Comment Period | 03/18/2020 |
Decision | 04/2020 (Estimated) |
Implementation | 05/2020 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mt. Hough Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations; Road Maintenance
Current Status:
Completed
Project Decision Information
Plumas Imperial Mining Plan of Operations
Decision Signed Date: 04/28/2020
Forests:
Plumas National Forest
Districts:
Mt. Hough Ranger District
States:
California
Counties:
Plumas
Legal Land Description:
T24N, R9E, Sec 18
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Leslie Edlund
39696 State Highway 70
Quincy, CA 95971
530-283-7650
ledlund@fs.fed.us
Last Updated: 11/19/2021