Golden Trout Temporary Bridge Placement
We are proposing to install an 85 feet long temporary bridge next to the existing damaged bridge. This will allow administrative and public access across the stream without resource damage. This will involve constructing approaches from both sides.
Project Summary
Location Summary:
The existing bridge crossing South Fork Feather River at Golden Trout was damaged when a large tree traveling down river struck the metal I-beam support causing an approximately 10-inches crack.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 09/13/2019 |
| Decision | 01/2020 (Estimated) |
| Implementation | 01/2020 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Feather River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Road Management
Project Activity:
Road Maintenance
Current Status:
Completed
Project Decision Information
Golden Trout Temporary Bridge Placement
Decision Signed Date: 01/27/2020
Forests:
Plumas National Forest
Districts:
Feather River Ranger District
States:
California
Counties:
Butte
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Herman Wendell
875 Mitchell Avenue
Oroville, CA 95965-4699
530-532-7466
hwendell@fs.fed.us
Last Updated: 1/31/2020