Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 05/19/2021 |
| Decision | 05/2022 (Estimated) |
| Implementation | 05/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (2), 36 Cfr 220.6(E)(2)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Feather River Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
PG&E Caribou Palermo Line Decommissioning Project
Decision Signed Date: 05/20/2022
Forests:
Plumas National Forest
Districts:
Feather River Ranger District
States:
California
Counties:
Butte; Plumas
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Erika Brenzovich
875 Mitchell Avenue
Oroville, CA 95965-4699
530-283-7622
erika.brenzovich@usda.gov
Last Updated: 5/20/2022