PGE Mt Hough Comm Site Line Reinstallation
Mt Hough Comm Site line (PGE) failed. Needs reinstallation underground in new trench.
Project Summary
Location Summary:
section 8, T. 25 N., R. 10
E., Mount Diablo Meridian
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/25/2024 |
Decision | 11/2024 (Estimated) |
Implementation | 11/2024 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Plumas National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
PGE Mt Hough Comm Site Line Reinstallation
Decision Signed Date: 11/01/2024
Forests:
Plumas National Forest
Districts:
Mt. Hough Ranger District
States:
California
Counties:
Plumas
Legal Land Description:
section 8, T. 25 N., R. 10
E., Mount Diablo Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Jacob Sax
159 Lawrence Street
Quincy, CA 95971-6025
5309278114
Jacob.Sax@usda.gov
Last Updated: 1/21/2025