Lucky Baldwin Hard Rock Lease
Proposed action involves building a 400 foot long haul road and installing barriers to limit access to the Lucky Baldwin Mine
Project Summary
Current Status:
Completed
Location Summary:
One half mile west of the Big Bear land fill on 3N16 NFS Road.
Project Milestones:
| Milestone | Date |
|---|---|
| Scoping Start | 01/18/2011 |
| Decision | 05/2011 (Estimated) |
| Implementation | 05/2011 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (8), 36 Cfr 220.6(E)(8)
Special Authority:
Not Applicable / Other
Lead Management Unit:
San Jacinto Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Minerals And Geology
Project Activity:
Abandoned Mine Land Clean-Up; Minerals Or Geology Plans Of Operations
Project Decision Information
Lucky Baldwin Underground Mine - Hard Rock Prospecting Permit/ Lease
Decision Signed Date: 05/02/2011
Forests:
San Bernardino National Forest
Districts:
Big Bear Ranger District
States:
California
Counties:
San Bernardino
Legal Land Description:
NE1/4 of Section 36, T. 3 N., R. 1 E., SBBM. Less than two acres of impact and the other 38 acres have no surface occupancy stipulation.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Raj Daniel
54270 Pinecrest Avenue
Idyllwild, CA 92549
909-382-2898
rdaniel@fs.fed.us
Last Updated: 6/28/2011